COBIAX technology was applied to the project “THE GRID – Office Complex” in Marousi, with a total area of 61,500 m2, expected LEED Platinum certification. The project concerns four (4) buildings and extends over three (3) underground and five (5) above-ground levels. In order to achieve the required dead load reduction and thus the construction of flat slabs, COBIAX concrete slabs were designed and constructed on four (4) above-ground levels. The total application area was approximately 5,000 m2 and concerned concrete slabs of 25 cm thickness to which the COBIAX CLS-P-130 type was applied.
Project description: THE GRID – Office Building Complex
Owner: NOVAL PROPERTY & BROOKLANE
Architectural Design: Foster & Partners
Structural Design: OMETE S.A.
Construction: TERNA S.A.
https://noval-property.com/project/the-grid-sygkrotima-grafion